Site development update

Please find below the latest update on current activities and works due to commence on site in the next few weeks.

Current activities

- Beard’s permanent offices and welfare facilities are now fully installed complete with Beard signage and logos

- The hoarding is being installed around the site and AELTC cabins boundary. Tarmac is being installed to the new temporary footpaths and the installation of the drainage for the wheel washing facilities near the main site entrance has commenced

- The ground has been prepared and the foundations for the new Clubhouse are underway

Forthcoming activity

- Work on foundations for the new Clubhouse will continue in the New Year

- Construction of the new roadway will begin and site hoarding will continue

- General deliveries to site will include drainage, aggregate, skips and concrete

For any comments/enquiries please email: communitytennis@aeltc.com

For any out of hours queries/concerns: contact

AELTC Event Control Room: 020 8971 2261 or

David Diffey (Beard's Project Manager): 07785625456