Community Tennis Centre Site Works Update

The courtyard buildings steel frame and glu-lam beans are now erected, so the shape and size of these buildings will start to materialise in the next week. The clubhouse building is moving forwards well with the second of the three slab concrete pours now completed. The walls on the first floor are also now being erected. Please find below an update to our current works and activities due to be carried out in the coming weeks.

 

Current Activities week commencing 27 June

- Continuation of steel and glu-lam frame erection

- Delivery of cross laminated timber (CLT) roof structure for the courtyard buildings

- Final first floor slab pour to the clubhouse

- Continuation of formwork to first floor walls on the clubhouse building. -

- Commencement of masonry to the courtyard buildings

- Striking of formwork to reinforced concrete walls in the courtyard buildings

- Exposing of foundations on the clubhouse buildings ready for masonry cavity walling

 

Saturday Working

 

As we progress on site, we will be continuing with our Saturday working to maintain progress and in the next period we will be mainly continuing with the reinforced concrete frame. We will be striving to keep any noise and disturbance, especially on these Saturdays, down to an absolute minimum. We appreciate your patience and cooperation as we continue our works on site.