CTC development works update 30 June 2023

Work activities week commencing 3 July

We are moving forward well internally with plumbing and electrical installation works ongoing as well as the continuation of the external envelope of the building.

The finishing trades are now well underway, working internally on carpentry and drylining.

  • Vertec / Bailey system progressing to front elevation.
  • Vertec/Bailey system progressing to front elevation.
  • Canopy roof carpentry complete and awaiting roofing system.
  • External paving completed to rear terrace.
  • Irrigation in progress including drip feed.
  • Landscaping and planting in progress.
  • Boundary fencing to cottage complete.
  • Tarmac to parking bays and footpath.
  • Acoustic ceilings in progress in conjunction with 2nd fix electrical.
  • Plaster and boarding to lift shaft high level.
  • Corridor ceiling grid installed, and ceiling tiles ordered.
  • Ceramic tiling to changing rooms/showers continues.
  • Floor tiling to changing/shower rooms.
  • Lift installation complete although awaiting commissioning.
  • Rack Room previously handed over.
  • Bleacher seating installed.

Future work activities

  • Bailey/Vertec to continue.
  • External flashings to Clubhouse and courtyard.
  • Landscaping and planting.
  • Timber cladding to courtyard.
  • Front entrance canopy roof
  • External groundworks to courtyard and front of main entrance area.
  • Irrigation and ducting.
  • Thermoguard to atrium.
  • 2nd fix all trades.
  • Floor finishes.
  • External doors to courtyard.

Saturday working

As we move into the finishes of the project, most of our works will become internal and as such will be less disruptive. Saturday working will likely to be required over the coming months, but we will do our absolute best to schedule any disruptive works away from Saturdays.

We thank you for your continued patience whilst the works are ongoing.