CSG development works update

CONSTRUCTION WORKS

- Construction of tennis court ground beams [photo right]

- Install services and drainage in-between courts

- Intumescent painting to steel structure Maintenance Building [photo left]

- Groundwork associated to services and drainage for maintenance building

- Continue to install irrigation and tennis court build-up material

- Continue excavation and installation of drainage swales

- Continue to pump water from site

 


DELIVERIES/COLLECTIONS

40-60 loads per day of excavated ground to leave site

Multiple loads of material deliveries


For any comments/enquiries please contact: communitytennis@aeltc.com
or for any problems out of hours,
AELTC Control Room: 020 8971 2666 or Vino (Careys Project Manager): 07885814663/07912504646