CTC Site Development Works Update

Works have now fully restarted after the Christmas break with a full team of trades in operation.  We are moving forwards well internally with plumbing and electrical installation works ongoing as well as the continuation of the external envelope of the building. Specialised trades including wall taping and covering, painting, glazing and glass work and flooring are underway. The installation of kitchen equipment has also commenced.

 

Work activities week commencing – 23/01/23

  • Continuation of plumbing and electrical works
  • Internal and external carpentry works
  • Plastering and general drylining works
  • Groundworks associated with main electricity switchovers
  • Trenchworks for irrigation pipework
  • Scaffolding adaptions and erection

Future work activities week commencing

  • Installation of curtain walling, remaining windows, and doors
  • Perimeter fencing works
  • Continuation of the activities listed above

Saturday working

As we move into the finishes of the project most of our works will become internal. Saturday working will still be required over the next months, but we will do our absolute best to keep any disruptive works away from Saturday. Your continued patience is much appreciated.