CSG Development Works Update 11 September

Site Works Update


Works to Tennis Court Block A are nearly complete with seeding works due to commence on 8th September
Drainage to the Sports Pitches is still ongoing and will be completed within the next 2 weeks
Soft landscaping to the Detention Basin and pitch side areas are progressing well and are on course for completion by the end of September
The Maintenance Building Service Yard has had fencing installed along with the paved car park area being completed ready for white lining works and final Tarmac laying
The Maintenance Building itself has had internal painting and tiling being carried out along with plumbing, ventilation and electrical services still being installed
We are happy to inform you that we are carrying out the below key activities to support the project in the coming weeks, please note that works to the Tennis Courts (loam installation and build up works) will be ongoing until 19:30hrs Monday-Friday in agreement with Merton Council;

Week 20
Soft landscaping works to the Detention Basin
Sports Pitch drainage installation
Court B build up works
Court G build up works
Maintenance Building services installation
Court perimeter fencing/railing works
Service road gate and fencing installation
Service road and yard Tarmac works
Site clearance works


Week 21
Soft landscaping works to the Detention Basin
Sports Pitch drainage and seeding works
Court B loam and seeding works
Maintenance Building service installation
Court perimeter fencing/railing works
Service Yard fencing installation
Site clearance works


For any comments/enquiries please contact: communitytennis@aeltc.com or for any problems out of hours,
AELTC Control Room: 020 8971 2666 or James Williams (Careys Project Manager): 07789925272
Kind regards
The AELTC/Careys Construction Team