CSG Development Works Update

Site Works Update

 

The last 2 weeks have been very productive on site whilst managing to ensure our workforce are maintaining social distancing.

Works to the maintenance building have pushed on with internal blockwork being completed and external cladding works progressing well.

The first phase of tarmac works to the Cannon Hill Lane entrance road has been completed and a fair bulk of the tennis court footpaths have been tarmacked to completion and paving works are progressing well.

Soft landscaping including tree and shrub planting has been ongoing and we have commenced with levelling the football pitch area.

 

We are happy to inform you that we are carrying out the below key activities to support the project in the coming weeks.

 

Week commencing 1st June

- Tennis court build up works

- Maintenance building cladding and internal service fit out

- Deep service installation to maintenance building

- Concrete and paving works between various tennis courts

- Irrigation installation to tennis courts

- Football pitch and basin area levelling and forming

Week commencing 8th June

- Maintenance building cladding and internal service fit out along with various external tank installation works

- Footpath formation works to the north of the maintenance building

- Paving works between various tennis courts

- Football pitch and basin area levelling and forming

- Tennis court loam installation activities

 

For any comments/enquiries please contact: communitytennis@aeltc.com or for any problems out of hours,

AELTC Control Room: 020 8971 2666 or James Williams (Careys Project Manager): 07789925272

 

Kind regards

The AELTC/Careys Construction Team